Managing resources
December 7, 2013 - 03:17 am
0 comment(s)
Hi folks,
Thanks for making such a great piece of software freely available!
I have a couple of questions that I was hoping someone could help me with . . .
I have a small team and a huge project so my timelines for project completion are going to be dictated by resource constraints. Given that projectlibre doesn't automatically adjust the dates when a resource is over-allocated, does anyone have some suggestions/tips/tricks for managing the over-allocation of resources?
Secondly, what are the 'assignment delay' and 'leveling delay' columns used for in the task usage window?
Thanks again.