Resource Start Finish

March 13, 2014 - 12:19 pm
1 comment(s)

Hi, I have a pretty fundamental noob question.

If I have a task with 2 subtasks that can be done in parallel, and both take half a day then I understand the task can be completed in half a day.

However, If I assign a resouce (in this case a person) to both subtasks, then the task will take a full day to complete.  These tasks are not depenancies of one another.  At the moment, ProjectLibre allows me to set the same resource to oth subtasks as the same time.  

Is there a way of stopping this (i.e. Having it automatically recaulculate the start finish when the required resource is already 100% utilised)?

 

Thanks