Start and Finish Dates
May 30, 2014 - 03:07 am
1 comment(s)
If you put in the calendar that resources can only work 2 hours per day, the cost rolls up correctly yet on the Gantt chart when you put in the duration in days, the start and end dates are not calculated correctly (like they don't respond to the calendar modification of 2 hours per day). Any suggestions?
1 Comment
Can you clarify or send the project file
I am not clear on your problem. Can you expand the comment or send the project file to [email protected]