Discussion

vacation days and timelines

February 10, 2014 - 01:57 am
1 comment(s)
Dear NAUC,
 
Project Libre looks very cool. 
 
I am trying to use it to plan a large writing project and the only remaining issueis how to account for holidays (ie my won) when I will not be working.
 
I have looked at changing the workdays on the calendar, but this seems only to change the time a given task takes, but does not seem to change the dates for a successor task.
 
Although I have searched using a few different keywords, I have not found a relevant posting.
 
Thanks in advance for your help and patience.
 
Kind regards,
 
BW

1 Comment

February 11, 2014 - 08:40 am

If you create a calendar and save it.... then apply the calendar to the project  and tasks you will not work on those days.  Let me know if that works for you.