Working/following days how to ?

February 13, 2013 - 22:18 pm
suljo
2 comment(s)

I want to plan something for example from 2/13/13 8:00 AM  to 2/18/13 5:00 PM; How can I also include at "duration" weekends days ?? By default is duration only woorking day (from monday to friday)...

I try everything at DURATION: '5 fd'...adns imilar from MS PROJECT, but it's not working???

 

2 Comments

February 15, 2013 - 19:36 pm

well what about changing "working time" from standard to 24 hours within the Calendar table ? This seems to allow you for week-end days to be integrated to your schedule

February 15, 2013 - 22:20 pm

You can create a new Calendar.  If you look in the ribbon you can select Calendar.  You can then modify the Standard calendar or create a new one based upon that calendar.  You can select Saturday and Sunday at the top and click on Non-Standard working time... this will result in changes to the working calendar if you apply this calendar on tasks, resources or projects.   You will need to specify this new calendar on those items....

 

Cheers,

 

Marc