Work contour
July 4, 2017 - 15:34 pm
0 comment(s)
Hello everybody
I have a question about the calculation of the "Work" of task with respect to the work contour selected.
Example:
I have a task with "Fixed Work". I created the task with the "work contour "Flat". If I change the "work countour" afterwards to any other type e.g. to "front loaded" the "Work" will be reduced and I have to set the "Work" to the correct value again manually.
Can anybody explain this behavior?
Kind regrads
Michael