I am trying to create a monthly budget forcast. I have the project set up and do the following:
1. Click Resource Usage
2. Zoom out so that I have 1 column per month
3. Right click in the right pane and unselect work, and select cost.
Now I have all my activities, their cost, and the month the cost occurs in, but I can't copy the cells out. Copy only gets the data from the left pane.
Any help would be appreciated.
Jim