Set budget and costs

June 10, 2014 - 10:10 am
1 comment(s)

Firstly, congratulations on ProjectLibre - I am finding it a very useful and intuitive tool - secondly, a very simple question - how do I set the resource overall budget and track costing?

 

budget

1 Comment

June 11, 2014 - 01:44 am

Thank you for the message.... If you have rates on your resources and
They are assigned to tasks... Baseline the project and that is your plan. There are a lot of reports and. Graphs to track the budget with earned value costing.