Hi,
I have a few questions
1. Is there a possibility to set up a fixed budget for entire project and track it how much of it was spend? (by adding tasks and assiging resources with hour rate)
2. I've created tasks with fixed work:
- task1 Work=20
why I can't make Actual Work > Work - in this way I could see that task took more time in reference to the scheduled work.