How do you do manual leveling?

1 comment(s)

I've read through the manual as well as searched discussions and It's clear that manual leveling is the only available option.  What I haven't found is how this is supposed to be done in ProjectLibre.

I have a project with 110 tasks and a dozen resources.  The histogram view tells me i'm overallocated, but I have to maually scroll through the Gantt chart or resource view to see what I should change.  There seems to be no way to manage this with an overview. If the histogram was clickable and ID the apporpriate task, that would be a big help,  Right now I'm just forcing this by manually allocating predecessors to force resource allocations.

Can anyone point me to an example or document?