How do you do manual leveling?
December 9, 2015 - 05:13 am
1 comment(s)
I've read through the manual as well as searched discussions and It's clear that manual leveling is the only available option. What I haven't found is how this is supposed to be done in ProjectLibre.
I have a project with 110 tasks and a dozen resources. The histogram view tells me i'm overallocated, but I have to maually scroll through the Gantt chart or resource view to see what I should change. There seems to be no way to manage this with an overview. If the histogram was clickable and ID the apporpriate task, that would be a big help, Right now I'm just forcing this by manually allocating predecessors to force resource allocations.
Can anyone point me to an example or document?
1 Comment
help with screen resolution
Hi,
I can't figure out how to write my own discussion, and can only see adding a comment so my apologies.
I use the software on a number of computers, and just downloaded it onto a lenovo laptop. for some reason the screen size is tiny when i open program and i can't find a way to make it bigger. ive tried to zoom, change screen resolution etc nothing is working.
any advice? desperatly need this to work on my new laptop.
thanks