I've read through the manual as well as searched discussions and It's clear that manual leveling is the only available option. What I haven't found is how this is supposed to be done in ProjectLibre.
I have a project with 110 tasks and a dozen resources. The histogram view tells me i'm overallocated, but I have to maually scroll through the Gantt chart or resource view to see what I should change. There seems to be no way to manage this with an overview. If the histogram was clickable and ID the apporpriate task, that would be a big help, Right now I'm just forcing this by manually allocating predecessors to force resource allocations.
Can anyone point me to an example or document?