1 Basic question re Resources allocation

Hi all,

Here is the little scenario I would like to clarify:

1. I create a 10 days task T1 with all default settings ( type= fixed units, duration=80hours, workload=80 hours)

2. If I assign one resource R1 to it, resource is allocated for 100% for the duration of the task. So far, so good.

3A. If I remove the resource R1 and THEN reassign 2 resources R1 and R2, both are allocated for 100% and the duration of the task drops to 40hours/5 days (task work remains unchanged at 80hours). So far, still good.