1 | 7 day work week calendar | I am having difficulty in creating a project which runs 7 days per week. I edited the calendar to produce a custom calaendar with working hours set at the weekend, but when I enter the duration of the work in the sheet, if more than 5 days it splits the work over the weekend. I do not want this to happen, the work runs 7 days a week am I missing something? |
wilwahabri | Asian User Community | Sep, 23, 2014 |