# | Title | Preview | Author | Groups | Updated |
---|---|---|---|---|---|
1 | RBS can not be saved | Dear ProjectLibre users, has anyone come across the issue of saving the RBS in 1.7? When I create in 1.7 a resource list of 54+ lines split into 10+ groups I am unable to save the structure of resources. When I open the saved .pod file I see the flat list of the resources. Simultaneously the customized order of the columns in the Gantt tabe got dropped, so that I see the default columns in the default order. No data besides the structures got lost. Any suggestions on how to remediate the issue? |
VVS | Global User Group | Feb, 16, 2018 |
2 | 7 day work week calendar | I am having difficulty in creating a project which runs 7 days per week. I edited the calendar to produce a custom calaendar with working hours set at the weekend, but when I enter the duration of the work in the sheet, if more than 5 days it splits the work over the weekend. I do not want this to happen, the work runs 7 days a week am I missing something? |
wilwahabri | Asian User Community | Sep, 23, 2014 |