1 Limited Resources and Task Completion Calc

Hi, I am new to ProjectLibre. I am wondering how to solve the following problem of a resource having a limited input on a project per day and the resultant period over which that task would be completed.

Example

Resource1 works 1 hours on a project per day.

Task duration = 8 hours.

Therefore, Task completion time should be 8 working days. If it started 30.10.13 then it would be completed 08.11.13 (8 working days later).

How do I implement this?

davetyler European User Community Sep, 23, 2014