1 | Limited Resources and Task Completion Calc | Hi, I am new to ProjectLibre. I am wondering how to solve the following problem of a resource having a limited input on a project per day and the resultant period over which that task would be completed. Example Resource1 works 1 hours on a project per day. Task duration = 8 hours. Therefore, Task completion time should be 8 working days. If it started 30.10.13 then it would be completed 08.11.13 (8 working days later). How do I implement this? |