1 Resource constraint and calendar

Hi all,

This sw looks great, but coming from MS Project I'm having some issues in finding the same functions.

1) Resources don't seem to be pipelined. Ie if I assign a resource to 2 tasks, these tasks can appear in parallel, even if I set the resource max to 100%.#

2) Sometimes the resource calendar does not work. eg in the standard calendar I set christmas as non working day and as working day in a "supplier" calendar. Still the "supplier" tasks skip the xmas day.

Any ideas anyone?

 

Thanks

 

Gam

 

Gubo Global User Group, European User Community Sep, 23, 2014