1 | Resources usage and assignements | Dear All, I am new on Project Libre. I have some problems in understanding how to assign resources. Should be the assignement be referred to the completion of a task or to the time available on the project? I'll make an example: I want to assign 3 resources on task A (which is actually a meeting). All 3 resources are full time and they will participate to the meeting. How am I suposed to assign the percetages? Thanks a lot! Elisa |