1 predecessor running parrel

HI Team Libre'

 

Have a strange request .

doing a project where there is predecessor runinng 2 weeks and its succesor starting a day after inintiation but it only allows me to set the successor date after the predecesor is complete. is there a way to do this with link the the two

 

Regards Damain(Johannesburg South Africa.)

 

 

mastaegore African User Community Sep, 23, 2014