My content

# Title Preview Author Groups Updated
1 Can I have a backward scheduled task in a forward scheduled project?

Quick question; I'm not sure I'm phrasing this right but, is there a way to have a backward scheduled task... in a forward scheduled project?  In other words; my project is primarily forward scheduled; where Task B is typically set to begin when the previous task (say: Task A...) is completed... but there are a few tasks, between which I would like to set up a dependency such that Task N is set to be *completed* AT THE SAME TIME that the previous task (Task M) is also completed.

ericker451 North American User Community Sep, 30, 2014