1 Question about interaction between material resources and task duration

I'm having trouble understanding the way assigning resources impact on durations of tasks.  For example, let's say I have already created a calendar with non default working time of 9.5 hours per day: 7.30am-12pm and 1pm-6pm.  I have also entered the duration option that 9.5 hours = 1 day.

I create a task which by default has 9.5 hours entered in the work column and 1 day entered in the duration column.  The start time is 7.30am and finish time is 6pm, which is what I would expect.

bennals Global User Group Feb, 08, 2016