1 Adding resources to fixed duration tasks

Hello,

I am struggling a bit with adding resources to a fixed duration task. Any help is appreciated.

Summary

If you have a fixed duration task, ProjectLibre does not appear to properly handle resource adjustment by work, only by units. 

...Unless I am missing something! Is this a bug?

Example

My goal is to add resources at less than 100% (units) to a fixed duration task. This is a pretty common situation in my projects. I am assuming here that:

Work = Duration X Units

evyxmsj Global User Group, European User Community Dec, 16, 2017