1 Constraints Analysis

Is there a way to score the quality of a schedule in ProjectLibre (i.e. number of constraints, number of tasks on critical path)?  How might one perform a Monte Carlo analysis (with data entry on the potential early or late days per task) to determine management reserve days (say before a critical constraint like a plant outage)?

jp4 North American User Community May, 23, 2016
2 Critical Path

I was a PE/PM for 25 years and worked 30+ projects primarily using Excel, MSProject and PrimaVera for project scheduling (dpending on project size).  The ProjectLibre Open Source effort seems very good to me.  Is there a way in ProjectLibre to set the filter for < x days of float?

jp4 North American User Community May, 23, 2016