Work field is incorrect

December 1, 2017 - 06:09 am
0 comment(s)

I included a column with field work and it shows incorrect values when compared with MS Project (checked in .mpp and .xml formats).
How can this be corrected?
Which is the equivalent field for work field in MS Project?
Apparently Libre "computes" the field instead of taking it from the file (shows 8 * duration in hours).
Can anyone help?