The ProjectLibre team has a strong interest in the South and Central American community.  One of our co-founders was in the Amazon this Summer and regularly travels in Central and South America.  Our past software is widely distributed in the region and we look forward to your joining this community.  You can also join the Global and other regional communities if that is of interest.

Image group
Discussion

Work field is incorrect

0 comment(s)

I included a column with field work and it shows incorrect values when compared with MS Project (checked in .mpp and .xml formats).
How can this be corrected?
Which is the equivalent field for work field in MS Project?

Discussion

Consideration of time difference in xml file

0 comment(s)

Hi, I need your help about xml file.

Discussion

Network Diagram Visualisation

5 comment(s)

Hi guys,

 

Discussion

Gantt time scale

12 comment(s)

How to change the time scale of GANTT

Blog

CIO Magazine:(ProjectLibre)is scalable from small business all the way up to Fortune 500 companies.

4 comment(s)

 ProjectLibre was noted in CIO magazine:  "The software is scalable from small business all the way up to Fortune 500 companies."   The

Discussion

support Resource conflict

1 comment(s)

Hello, I need support, I want to know if it is possible to create a single array of resources and share them in several projects and at the same time indicate conflicts when I want to use the same resource at the same time within different projects

Discussion

Task and resources scheduling

0 comment(s)

Hello.

Discussion

FF and SS Dependencies

0 comment(s)

Hi, I am just starting with project libre, and everything looks great, easy to use; Thanks for this great tool!!

Iam having a problem with task dependencies, and, if someone could help me, it would be great.

I ll try and explain it simply ))

Discussion

The task finish date moves away from another task it dependent on when using Intend

5 comment(s)

As I mentioned,

When I use intend the finish date of the dependent task stops being dependent on the start date of the final task.

And it really doesn't matter whether the tasks get linked to another tasks when intended or they are just intended not getting linked to any task.

Discussion

Is it possible BCWP > ACWS or BCWP > BCWS ?

0 comment(s)

Example:
A task involves the construction of a wall.
The wall will have 10 rows of bricks.
The planned effort is 10 days for the construction of the wall and it will be necessary 1 day for each row of bricks. One mason will be allocated at this task.