How to delete, re-assign or edit resources once allocated?

0 comment(s)

Hello,

Brand new at this program. I have created a workflow including assigning some "Resource"s to tasks in a construction environment. Now, one of the "Resource"s has left the job and ProjectLibre does not seem to allow me to edit in any way the task resource.

Discussion

How add Tag Name In Gantt Chart

0 comment(s)

I was trying to add Tag name or you can call it as Task in Gantt chart. I would want to share the only gantt chart. Since there are no much information we could describe in gantt chart, i unable to share the same. I will be grateful if anyone suggest me to proceed. 

Discussion

S-curve

0 comment(s)

Hello everybody. my o.s. is win10

How can I create the S-line in projectlibre from the gantt ? My activities include the cost, duratin,.. and I can show the column 'cost' in the window

Discussion

Salesforce Integration

0 comment(s)

Does ProjectLibre integrate with Salesforce?

Discussion

Will Cloud Be Installable on Private Server

0 comment(s)

If an organisation does not wish to use a vendor cloud, will the server product be available for installation on a private server?

 

Thanks

Discussion

Duration Display

1 comment(s)

How can we display the "Duration" in minutes or hours ?

Discussion

Date Format [Again]

0 comment(s)

Hi All,

Can anyone tell me either as a proper fix or Java hack, how to change the default long date format including time to a simple date in Project Libre 1.7  

Discussion

Project Status Measures - Projectlibre question

0 comment(s)

How do I update actual costs (AC or ACWP) in Projectlibre?

Discussion

Update of tasks after defining holidays

0 comment(s)

Hi, I did a search in this topic and did not find an answer.  Excuse me if there is one and I did not find it.  I am defining holidays in my calendar and affected tasks get their task duration modified rather than the task dates modified accordingly.  Tasks have been left default with no dates en