1 Resource Allocation

Hello,

Why does a 15day task with two resources divide into 7.5days each, I would like it to be 15days each?

Thanks

Oglander North American User Community, European User Community Sep, 23, 2014
2 Allocation of tasks to resources

I have created a project with a number if single day tasks, a lot of dependencies amongst them, various priorities, and a single resource to do them. The intention is to get a good sequencing of the many interrelated tasks.

However, part from dependencies causing one task to be scheduled after it predecessor, large numbers of tasks are being scedhuled on the same day, even though each task is defined with 8 hours duration and 8 hours work.

How do I tell it that this resource can only do 1 task a day?

 

squeakoz Global User Group Sep, 23, 2014