91 | Start and Finish Dates | If you put in the calendar that resources can only work 2 hours per day, the cost rolls up correctly yet on the Gantt chart when you put in the duration in days, the start and end dates are not calculated correctly (like they don't respond to the calendar modification of 2 hours per day). Any suggestions? |
Yar | North American User Community | Sep, 30, 2014 |
92 | Change Font Color of Task | Is there a way to change the font color and/or background color of a task? |
wrbird | North American User Community | Sep, 30, 2014 |
93 | Project libre French documentation | Hello, I'm starting with project libre. The link to access to the French documentation is not available. Does someone know where i could find the latest version of this document ? Thanks al lot ! |
cjolivet | European User Community | Sep, 30, 2014 |
94 | Getting Help for newbie PL user? | Hi, As a newbie to PL, I clicked on the help button and my chrome browser popped up an SSL error: |
simonkbike | Global User Group | Sep, 30, 2014 |
95 | How to define days off for a resource ? | Hi all, how can i define the days off/vacancies/holidays for a resource? Now i defined a date from which i declared 0% but it didn't work.
|
stefano.mora | European User Community | Sep, 30, 2014 |
96 | UK Localisation | Hi Is it possible to change date formats to dd/mm/yy and also use £ rather than $? Colin |
colinparker1967 | Global User Group | Sep, 30, 2014 |
97 | Completing percent complete filed changes tasks dates | I'm facing a weird issue: in some cases, when I complete a field "Percent complete" tasks being moved on the chart. Happens mostly at FF relations. Example on a picture attached. Does anyone have a clue how to solve this issue? I'm using 1.5.9 version (Windows 7) |
krzysio99 | European User Community | Sep, 30, 2014 |
98 | Changing timeline view | I am a first time user. Can anybody tell me how to change the schedule timeline view from weekly to monthly in the GANT chart? I am working on a lomg term project and need to compress the calendar view into monthly increments. Thank you |
lhamroun | Global User Group | Sep, 23, 2014 |
99 | Multiple Projects Question | Is there a way to work with muliple projects as indivduals but combine them such as using a Master Project and sub-projects in MS Project? |
sraboltcc | North American User Community | Sep, 23, 2014 |
100 | Changing Calendar Hours | I'm not sure if I missed something but I had a project that was built with the Standard 5-day calendar. I changed it to six working days with the creation of a new calendar and saved it. I then went into Resouces and changed the working hours of all workers, but the GANTT chanrt did not reflect the change until I closed the project and reopened it. Is this the intended behaviot or did I miss a step? Thanks in advance. Robert |
rjvelpasotx | North American User Community | Sep, 23, 2014 |