1 | predecessor running parrel | HI Team Libre'
Have a strange request . doing a project where there is predecessor runinng 2 weeks and its succesor starting a day after inintiation but it only allows me to set the successor date after the predecesor is complete. is there a way to do this with link the the two
Regards Damain(Johannesburg South Africa.)
|