1 Sharing projects with MS Project and back again.

I'm sharing planning with a project manager at work who's using MS Project 2010.

He has altered an 8 hr task, asigning 4 hours per day on two seperate days.

When we open this ammended file again in ProjectLibre the taks is now 16hrs long with 8hrs on each day.

Any idea why this is happening please?

Does anyone have any specific tips for sharing plans between MS Project and ProjectLibre?

THanks,

 - Regan. 

regan Global User Group Sep, 30, 2014