1 | Unable to update task | I can't set work completed to 100%. Gets reset to random value ! I'm using version 1.5.9. I have a task that I want to update and adjust the work completed percentage. When I select the task and click on update I get the update box ok, but when I change percent completed to 100% and then close the box, the value is auto adjusted to a random value% If I then reopne the box and try again, I get a different auto adjusted value : 77%. |
pcarew | North American User Community | Jan, 11, 2015 |
2 | Grouping tasks by ressource names: bug/improvement | Hello, I'm quite new to Project Libre and I have to say that it does almost everything I need. Thanks a lot for all the efforts done ! |
stephan | Global User Group | Sep, 23, 2014 |