1 | How does project libre calcuate durations? | I have a project with 1 task. It is a fixed work task that has a WORK of 8 hrs. I assign it a resource which works 4 hr/day.
I expect the duration to be 2 days. Instead, the duration is 1 day and the resource is shown as 200% allocated on that day on the resource histogram.
How would I make Project Libre spread that 8 hr task over 2 days as it should?
------------------------ As a test I made a new project I added one task...set it to Fixed Work and set the work to 24hrs. The task shows a 3day duration |