1 Task durations

Is it possible to assign whether a task duration is including weekends and others as exclude weekends? In my case, the workforce will work week days only. However, if I pour cement, it need 14 days to cure, So I need to include weekends in the cure period.

Nutzman African User Community Aug, 19, 2016