My content
# | Title | Preview | Author | Groups | Updated |
---|---|---|---|---|---|
1 | Setting Resource Availability | Hi, I have just started to take a look at ProjectLibre and have a question regarding changing resource availability. I would like to set the availability for individual resources to 0% for example when people take vacations. The Resource Information form has 'Availability', but if I enter a start date with 0% and then a later end date with 100%, there is no change in the resource availability displayed in the resource histogram and tasks are not lengthed to allow for the vacation. Any suggestions as to what I should be doing would be great. |
IShotUK | European User Community | Sep, 23, 2014 |