I am using Project Libre for a private project and I am working on it out of normal working time. Even if I set all calendars to 24 hours or to special working time, there is no possibility to set worked time on sundays. The tool doesn't accept sunday work time, at least as far as I see. Is there a special trick to change this?
Setting up a new project, first time user. After saving a start up task list starting August 1 2017, all good. Opened the project later, task dates \ok but the Gantt timeline started in 2022 not 2017, a five year shift. How can \i correct this short of starting over?
I am updating a schedule and want to set some of the starting dates prior to today. When I pull up the calendar and selected the date I want, it will not accept a date before today. What do I need to do for this?
I am trying to set up a seed file for future projects and I will need to adjust the start date for the new projects. When I attempt to do this, I am going into Task/update. The task has a start date pull down but it will not change. this is very frustrating because much of my resource information is redundant from project to project and I would like it to be populated in new schedules.
10 Comments
Time Scale.
What do you call the time scale, the setting of days?
Time scale
How can I modify the time scale?
Print
How can I get the gantt chart and the spreadsheet to print using full size paper??
Zoom in Zoom Out
Printing
How can I make it print to look just like the picture above??
How to set the calendars when you work some hours during weekend
Hi everybody,
I am using Project Libre for a private project and I am working on it out of normal working time. Even if I set all calendars to 24 hours or to special working time, there is no possibility to set worked time on sundays. The tool doesn't accept sunday work time, at least as far as I see. Is there a special trick to change this?
Thank you in advance for your intent of solution.
Claudia
setting the start date for the Gantt chart
Setting up a new project, first time user. After saving a start up task list starting August 1 2017, all good. Opened the project later, task dates \ok but the Gantt timeline started in 2022 not 2017, a five year shift. How can \i correct this short of starting over?
thanks, Art
Setting Time over 5PM to plan night work
Hi
I get a problem with planning time over 5PM, i put the calendars up to 24 hours but i'm not able to give a end time with 6PM
Where is the problem what i'am doing wrong??
thanks
Manfred
Schedule Update - set date prior to present
Greetings.
I am updating a schedule and want to set some of the starting dates prior to today. When I pull up the calendar and selected the date I want, it will not accept a date before today. What do I need to do for this?
Thanks,
Ross T
Changing the Start Date
I am trying to set up a seed file for future projects and I will need to adjust the start date for the new projects. When I attempt to do this, I am going into Task/update. The task has a start date pull down but it will not change. this is very frustrating because much of my resource information is redundant from project to project and I would like it to be populated in new schedules.