I'm new to ProjectLibre and have created a project and I want to know if there is a way to remove ALL time constraints from a task.

Even with all links deleted, the Start Date could not be changed (I would change it manually and it would go back to what it was) unless I selected the "As Soon As Possible" constraint.  However, with this selected, all of the Start Dates reverted to the starting date of the project and could not be changed from this unless I linked tasks together.

Thanks in advance.

Robert

 

constraint

2 Comments

May 16, 2014 - 09:04 am

You should check the documentation or videos.... you should be able to do what you wish

May 20, 2014 - 22:08 pm

If you don't have a constraint or a predecessor the Start as Early as Possible will put the task at the earliest project date which is the start.  You can drag the task and you will see a constraint icon on the spreadsheet.