Constraints Question

2 comment(s)

I'm new to ProjectLibre and have created a project and I want to know if there is a way to remove ALL time constraints from a task.

Even with all links deleted, the Start Date could not be changed (I would change it manually and it would go back to what it was) unless I selected the "As Soon As Possible" constraint.  However, with this selected, all of the Start Dates reverted to the starting date of the project and could not be changed from this unless I linked tasks together.

Thanks in advance.

Robert

 

Discussion

Task Constraint Issue/Question

1 comment(s)

I having an issue creating a task that I want to start exactly 5 days before another task.   I attempted to us a FS with a lag of 5 days.   If I leave both at as soon as possible the first task goes to my project start date.   I set task one to as late as possible and it changed the date to 2010?   Is there an issue or am I doing something incorrectly.