Task Constraint Issue/Question
January 2, 2013 - 12:05 pm
1 comment(s)
I having an issue creating a task that I want to start exactly 5 days before another task. I attempted to us a FS with a lag of 5 days. If I leave both at as soon as possible the first task goes to my project start date. I set task one to as late as possible and it changed the date to 2010? Is there an issue or am I doing something incorrectly.
1 Comment
Creation of task
I think solution is in your question because task always define some of the limit of days where you can set to certain date and manage so need to check again.