1 | Pulling in schedules (10hr work days) | Hi, I've create a project using the standard settings (8hr work day). I found that project completion date is too far. I'd like to try and pull in the schdule by increase to a 10hr work day. I tried a number of things but can't seem to get it to pull in. In the calendar options, there is a field to change the work day to 10hrs. Once I do this I see the durations get reduced, but the start/end dates don't change so the end date remains the same. |
tbitzanis | Global User Group | Sep, 23, 2014 |