1 How to change number of workdays per week?

Hi All

 

I have just started using Project Libre. I would like to change the number of work days from the default 5 to 6 (Saturdays are also working days). I am not able to get this information from the on-line help

How to do this?

Thanks in advance

Regards Ganesh

 

 

M.Ganesh Global User Group Sep, 23, 2014
2 How to edit a gantt chart

Hi,

 

first time user. trialling before i commit to purchase MS project as hoping i can avoid the purchase.

 

i have created a project and gantt chart. Truoble is, the gant chart is displayed in weeks and i would much prefer monthly overview so i can see more on the 1 page. Is there a way to do this as the editign options seem non existent.

 

regards

 

Jamie

jamie0001593 Global User Group Sep, 23, 2014