1 | Can I have multiple Hours Work by Day Settings? | I have a project with multiple people (resources) assigned to it. One person can work on the project all day, but another can only work 4 hours per day. How can I set that up in ProjectLibre? If I go to Calendar and click on options I can indicate how many hours per day to use, but this setting appears to be a global setting. When I change it it affects all calendars. I've tried it on new calendars based on the Standard Calendar and on Calendars I started from scratch. Any help would be appreciated. Brian |
bdokter | North American User Community | Sep, 30, 2014 |
2 | Completing percent complete filed changes tasks dates | I'm facing a weird issue: in some cases, when I complete a field "Percent complete" tasks being moved on the chart. Happens mostly at FF relations. Example on a picture attached. Does anyone have a clue how to solve this issue? I'm using 1.5.9 version (Windows 7) |