The ProjectLibre team is fostering a vibrant international community of users.  You can keep up to date by joining the Global User Group. We will post updates, news, events, blogs and many other specific informative in the Regional User Groups.  We look forward to your joining the ProjectLibre community!

Global User Group
Discussion

Project budget

4 comment(s)
Hi, I have a few questions 1. Is there a possibility to set up a fixed budget for entire project and track it how much of it was spend? (by adding tasks and assiging resources with hour rate) 2.
Blog

ProjectLibre: New website and updates

4 comment(s)

ProjectLibre new website and progress What a great new website we have at ProjectLibre! There are a lot of changes and improvements at ProjectLibre. I wanted to thank Tom Tran and his team who are partnered with my company Propeople.

Discussion

Manage overtime

2 comment(s)

Hi,

I have been looking how to manage de overtime of the resources and the only thing that I have found is only to place the overtime rate. I have the following doubts:

1. How can I see how much overtime my resources have used?

Discussion

New at ProjectLibre. Is it possible to create a calendar view of tasks ?

0 comment(s)

Hi,

I am new in ProjectLibre. I have setup several projects and wanted to to know if it is possible to create a daily task list per resource of overall. Can tis be used to organize the daily activities and how.

Discussion

Struggling to apply multiple resources with different work commitment to one task

0 comment(s)

Dear All,

Discussion

grid for better view calendar/text

1 comment(s)

Is it possible to show a grid on the calendar ? It's not comfortable to connect the text with the durations .

Thanks

Discussion

Update Task issue

2 comment(s)

ProjectLibre is great and I'm only having one issue. When I use "Update Tasks" and I enter the "Actual" Start date and time the "Original" Start date and time changes to the "Actual" start date and time I just updated. Is this a bug or am I doing something wrong?

Discussion

Language Setting

1 comment(s)

I'm a new user, from South America. I'm interesting about de language settings. For what I could read on the net, java runtimes should get the language info from the LOCALE settings of the computer, but this doesn't happends in my PC.

Discussion

How to set durations in hours instead of days

2 comment(s)

Can anyone tell me if I can set my project to use hours instead of days? I've a situation where I had allowed one day for a task which I then completed in only half a day.

Discussion

Conversion of .pod file to Ms xml format removes someof the tasks assignments

6 comment(s)

Conversion of .pod file to MS xml format  removes some of the tasks assignments.  The resource name columns go blank  for some of the tasks which can be seen when you open the xml back using Project Libre