1 Possible bug & work-around

Resource usage view - is this the intended functionality?When viewing resource usage (I have resources organized into 4 groups), the resource usage window does not seem to show the task usage for all of the resources by default, only those tasks assigned to a top-level group.  If I want to see the resource utilization for one or more individual resources, I need to select the appropriate rows in the resource window. 

Alan Lawee North American User Community Apr, 06, 2016
2 Question about interaction between material resources and task duration

I'm having trouble understanding the way assigning resources impact on durations of tasks.  For example, let's say I have already created a calendar with non default working time of 9.5 hours per day: 7.30am-12pm and 1pm-6pm.  I have also entered the duration option that 9.5 hours = 1 day.

I create a task which by default has 9.5 hours entered in the work column and 1 day entered in the duration column.  The start time is 7.30am and finish time is 6pm, which is what I would expect.

bennals Global User Group Feb, 08, 2016
3 Percent complete

Hello, I try to import a .mpp (2007 format file) but the column "% complete" does not populate in ProjectLibre. I have downloaded the latest version. I tried with "% work complete" but the same, all percents are "0 %" I use the french version. Any idea how to import the "% complete" information from a Microsoft project file? Thanks for your help

sebng European User Community Sep, 23, 2014