1 | Clarification needed regarding Resource availability units under resources main page in project libre | Hi, I have a simple question:(May be my understanding is wrong) 1)I have reource R1 assigned to Task 1 2)Suppose task T1 effort is 2 days 3)In the resource availability tab under resources menu (I did not double click task and assign-i DIRECTLY went to resource availability tab and mentioned max units as 50%) 4)Now in Task side assign this resource-I expected that the number of dates move to 4 days-technically 50% each day. 5)But looks it does not change.It still shows 2 days. 6)Am I doing something wrong here? |
s.subbarayan | Global User Group | Jul, 31, 2015 |