The ProjectLibre team has a strong focus on building the European Community.  We are co-founded in Europe and in the past have found our open source alternatives to be very popular on the Continent.  You can join both the Global User Group and also the European and other user groups.  We will be posting specific information relative to your user goup.

image group
March 6, 2013 - 16:11 pm
0 comment(s)

terminal server and silent install

Hi everyboby,

I want to install project libre on our citrix terminalserver farm. 

Here some specifications:

- Java 1.7 update 17 (always the last release)

- Windows server 2003 R2 terminal server (with Citrix)

 

February 14, 2013 - 00:03 am
4 comment(s)

Changing time unit

Hi everyboby

I'm a newby. I'm wondering if it is possible to change the time unit form day to week of month. For some quite long project a daily schedule is a nightmare to manage.

Cheers

February 13, 2013 - 22:18 pm
2 comment(s)

Working/following days how to ?

I want to plan something for example from 2/13/13 8:00 AM  to 2/18/13 5:00 PM; How can I also include at "duration" weekends days ?? By default is duration only woorking day (from monday to friday)...

January 23, 2013 - 19:35 pm
0 comment(s)

Title block

Hi,

How do I move the chart down the page to allow me to put a project title above the chart? And what have I done that makes my chart print in red rather than blue? I can't find a colour choice anywhere.

Cheers.

January 3, 2013 - 21:48 pm
1 comment(s)

Elapsing Time

When I put in '1ed' (1vd in Dutch) in the duration column in the Gantt then it expands to 3 days (of 8 hours) and also a 3 days graphic bar.

I expected to see 1 day of 24 hours and so a 1 day bar.