The ProjectLibre team is fostering a vibrant international community of users.  You can keep up to date by joining the Global User Group. We will post updates, news, events, blogs and many other specific informative in the Regional User Groups.  We look forward to your joining the ProjectLibre community!

Global User Group
Event

New Release updates

0 comment(s)

Hello,

any updates on the newelease of projectlibre? Any chanses to evaluate a beta version soon?

 

regards

Discussion

Clarification needed regarding Resource availability units under resources main page in project libre

1 comment(s)

Hi,

I have a simple question:(May be my understanding is wrong)

1)I have reource R1 assigned to Task 1

2)Suppose task T1 effort is 2 days

Discussion

How to choose columns shown for a file when it is opened?

3 comment(s)

Discussion

MSI Shortcut Table

1 comment(s)

Hi all,

Discussion

How to save changes to PERT and WBS diagrams?

3 comment(s)

I am not finding a way to save my changes to the layout of Network (PERT) or WBS diagrams. I reorganize them to how I would like them to appear, but when I go to print PL automatically reverts back to its default configuration.

Discussion

Can I format the date and time display

3 comment(s)

Good day, I am using ProjectLibre for the first time. Is it possible to remove the "time" from the default display and only display the "date"? I saw a discussion on this topic last night but cannot find it again. If my memory serves me right it was earmarked for future development.

Discussion

Gantt chart

2 comment(s)

Hi

 

Is there a way to create tasks but without time with start and end date ? I mean when finish one task starts the next in the sequence .

 

Discussion

Change language

2 comment(s)

Hello

I installed the program in Portuguese. How can I change it into English.

It would be nice not to change regional settings from the computer tough.

 

TY

Discussion

Removing times from Start/Finish Columns

2 comment(s)

Is there a way to remove the times in the Start and Finish columns, leaving only the dates?

Thanks!!!

Discussion

Resources and Scheduling?

2 comment(s)

Why is it that resource allocation has no affect on scheduling? Perhaps I'm missing something but in my use case (where there are many specific tasks which do not necessarily depend on each other, but must all be done by the same person) the gantt chart scheduling doesn't seem very intuitive.