The ProjectLibre team is fostering a vibrant international community of users.  You can keep up to date by joining the Global User Group. We will post updates, news, events, blogs and many other specific informative in the Regional User Groups.  We look forward to your joining the ProjectLibre community!

Global User Group
January 26, 2013 - 01:19 am
0 comment(s)

adapt workload to users disponibility

I've been tesing ProjectLibre and I find it very usefull, so first thanks guys. I will use it for teaching, so I will spread its use.

 

January 24, 2013 - 02:26 am
3 comment(s)

How is BCWP calculated

How is BCWP, ACWP, BCWS calculated?

In ProjectLibre 1.5.3 on Ubuntu , I do the following:

1. Create task of 1 week
2. Assign it to a ressource with a salary of 10 euros per hour
3. Cost ends being 400

January 15, 2013 - 08:38 am
4 comment(s)

relative timeline in weeks?

Is it possible to use a relative timeline in weeks for example?. That is, instead of full dates (for starting/ending and duration of task) use simple numbers indicating the week from the start of the project (which should be week 0).

 

January 10, 2013 - 12:49 pm
4 comment(s)

one page summary of multiple projects

I'm overseeing multiple projects with different project managers.

I would like to generate a summary list of all the projects in one view or one page.

January 3, 2013 - 21:48 pm
1 comment(s)

Elapsing Time

When I put in '1ed' (1vd in Dutch) in the duration column in the Gantt then it expands to 3 days (of 8 hours) and also a 3 days graphic bar.

I expected to see 1 day of 24 hours and so a 1 day bar.

December 28, 2012 - 07:27 am
5 comment(s)

Export gantt in a viewable format

 First of all, congratulations for the success of ProjectLibre! I've been usin OpenProj and now I am switching to PL :)