Discussions

North American User Community

The ProjectLibre team was co-founded in Silicon Valley.  We have traditionally seen over 40% of the users in our open source projects come from the United States.  We will be posting NA specific information in the User Group.  You can join other groups as well if you are interested.

 

image group
November 4, 2013 - 05:02 am
8 comment(s)

Update task completion with actuals

How do I update a task that finishes ahead of schedule without having to change the planned duration? I've tried the obvious step of selecting a task and pressing the update button.
November 3, 2013 - 00:19 am
1 comment(s)

Printing Resource Usage

I am new to ProjectLibre and want to know if the Resource Usage view can be printed to view what resources are needed when and how much per day - want to prevent overscheduling resources.

Thanks

 

October 17, 2013 - 20:40 pm
3 comment(s)

Microsoft project 2013 support

Hello

I am using ProjectLibre Version 1.5.7 for both Microsoft Windows 7 and Linux (Ubuntu).  Is it supported for Microsoft Project 2013 files?  If I load a 2013 file the UI gets stuck at the loading page. 

Thanks

August 28, 2013 - 22:47 pm
2 comment(s)

Locating Error Output / Log File

Hi, Where does Error output go? I'm trying to automatically generate the initial project schedule. When I try to open the generated XML file, I get a progress bar and then nothing. How can I find out where the problem in the XML is?

August 9, 2013 - 03:18 am
9 comment(s)

Resource Allocation

Hello,

Why does a 15day task with two resources divide into 7.5days each, I would like it to be 15days each?

Thanks