151 | Calendar Defaults - set my own "defaults" | Either I'm missing something very basic or, the program shoves its interpretation of what a calendar's defaults should be down our collective throats. |
heviiguy | Global User Group | Sep, 23, 2014 |
152 | Cast in overtime ProjectLibre | Hi all How is the launch of overtime in ProjectLibre? |
Hezequias Vasc… | Global User Group | Sep, 23, 2014 |
153 | Paste Text into Project Libre Notes | I am not able to paste text from .doc or xls or other sources into notes. Is there some way to do this? |
cgketchum | Global User Group, North American User Community | Sep, 23, 2014 |
154 | Export to MPP or save as MPP | Hi All, First of all let me congradulate the ProjectLibre team for this wonderful product. This is very good and helpful. I have started loving it. Well , I am new to Project management and asked to develop a project plan. I have completed it and sending it to my Senior Manager for further approvals. He wants the file in MPP format. Does any future available to export/save as MPP ? Also, the tasks are not appearing fully when i take the report ( Report - > Task Information - > Default ) . Is there a character limitation ? The same happens when i export to Excel. |
ashokabl | Global User Group, Asian User Community | Sep, 23, 2014 |
155 | How to create and manage a projects budget in the Project libre software? | Can someone please assist me with the following : How to create and manage a projects budget in the Project libre software? any links to tutorials or any other material will be very helpful. Thanks. |
Abro369 | Global User Group, European User Community, Asian User Community | Sep, 23, 2014 |
156 | Changing currency in ressource spreadsheet | Bonjour I installed Project Libre in french on my mac, I am defining the ressources in my project and the Euro currency symbol is displayed, how to change the symbol to $ dollars? Thank you Alain |
infodesa | Global User Group | Sep, 23, 2014 |
157 | How to filter all current tasks? | Hello! Is it possible to create a custom filter? I need to filter out all of the current urgent tasks. They must satisfy following requirements:
How can I do this? Thank you! |
olegcrew | Global User Group | Sep, 23, 2014 |
158 | 7 day work week calendar | I am having difficulty in creating a project which runs 7 days per week. I edited the calendar to produce a custom calaendar with working hours set at the weekend, but when I enter the duration of the work in the sheet, if more than 5 days it splits the work over the weekend. I do not want this to happen, the work runs 7 days a week am I missing something? |
wilwahabri | Asian User Community | Sep, 23, 2014 |
159 | Best way of share project info | Hello Community, im starting here to use project libre as my main tool for project management, at the same time im trying to follow PMI principles, anyway my question for debate is: What the best way for share project info (tasks, progress, etc) with stakeholders ? There is any way to build a project portal ? (like the sharepoint for the team foundation system if you know). Most of i want is for people who has assigned tasks, a quick way to see what they have to do.
Thanks! Enrique
|
eferreyra | South & Central American User Group | Sep, 23, 2014 |
160 | Assigning Manhours Rather Than Setting Days | I am working on scheduling a project and am not exactly sure on the dates of each task yet. I have broken the project into many small tasks. I have an estimate on how long each task will take. Since the tasks are controlled by the project deadline, I want to be able to assign a quantity of resource types (like: programmer) rather than assigning names. I want to do this without overscheduling a resource by naming it too many times. |
Josh111 | Global User Group, North American User Community, African User Community, Asian User Community | Sep, 23, 2014 |