161 Date Format It is unfortunate that Project Libre does not have the facility to change the start and finish date formats to Day/Month/Year and the option to remove the time Barry Freeman African User Community Sep, 23, 2014
162 Timeline in minutes/hours

Hello

I am using "projectlibre" for a project that last just a few hours.

Using zoom in/ zoom out options, it is possible to  change the visible scale, but it is not enough to see the Gantt chart in detail.

The zoom in option does not go any furhter.

Can we do something to zoom in even more on the Gantt chart? Is there an option to change the scale into hours or minutes?

Thanks

fidjisland Global User Group Sep, 23, 2014
163 How to change Calendar Working days and Working time for all days.

Hi all,

My working time is entirely different than default one which one has in Project Libre.

My working days are Monday to Saturday.

My Working Hours is 10:00-14:00 and 14:30 - 20:00

How can i change the above timings and saturday as working day in that.

Please help me on this.

thanks in advance.

Mahalingam.A

 

devmaha Asian User Community Sep, 23, 2014
164 License

Is there any license of using ProjectLibre on Client pc. llike Windows 7/xp. Is it fully FREE , pls confirm

srasini Global User Group Sep, 23, 2014
165 Quick question - answer may be obvious

I've got a quick question about ProjectLibre.  I want to set an absolute date for the Finish column and basically work backwards from that.  For example; an entire project has to be completed by, let's say, October 1.  I'd like to set a hard date in the Finish column and then have ProjectLibre calculate, based on the number of days I enter, the absolute last day a task would have to be started to meet the Finish deadline.

Is that doable the way I'm describing it?

bpb21 North American User Community Sep, 23, 2014
166 Adding Costs

Hi, 

I am new to ProjectLibre and i would like to add costs to my Gantt chart. I have seen the $0.00 section but cannt find where to put this in. 

Also does this work on a per hour basis or when you add resources will this also add to the cost of the project?

I hope someone can help, it is a shame there isnt a turorial or something on how to use the software. It looks like good software to have but it is taking me a long time to work out how to do things. 

Thanks

Deasha

Deasha Global User Group Sep, 23, 2014
167 Indent and Outdent bugs

I'm sorry to say that this product is NOT user friendly. I downloaded the app last evening and started to populate tasks within the "Name" field. I then wanted to create the hierarchy and add subtasks but every time I "Outdented" a task, the task was removed from the line and taken to the bottom of the all of the tasks. I tried working with it several different times and have just been frustrated with my results. Also, the mouse scroll does not work on the page, but I have to go to the side bar to scroll - Frustrating. 

xturner Global User Group, North American User Community, European User Community, Middle East User Community, African User Community, Asian User Community, South & Central American User Group Mar, 25, 2023
168 How does one configure ProjectLibre?

Amongst other things, it would appear that one cannot change simple things such as currency symbol, time units (hours vs. days), etc.

I'm uninstalling this software. Maybe I'll try again in a year or so...

chrisdev African User Community Sep, 23, 2014
169 Custom Fields in the Gantt Chart

I am new to Project Libre.  When I have used Microsoft Project in the past, I have leveraged custom fields in the Gantt chart such as Man Hours, & like to see the % Work Complete in the Gantt Chart.  However, I cannot figure how to modify the columns that are listed in the Gantt Chart.  Can this be done?  

I am on a Mac OS X version.

Thanks.

 

Kevin

kholla44 North American User Community Sep, 23, 2014
170 Export gantt in a viewable format

 First of all, congratulations for the success of ProjectLibre! I've been usin OpenProj and now I am switching to PL :)

I like the export as pdf function, which is good for printing it out. The problem is that when there are a lot of tasks and the duration of the project is long, the gant elements are very far from the task name, which is only in the first page. Would it be possible to add the label also at the start of every gantt bar? That would make the pdf view much more friendly!

rsisto Global User Group Sep, 23, 2014